# Brazilian municipal cable removal operations

> Developing situation record from CLSTR: https://clstr.news/situations/brazilian-municipal-cable-removal-operations
> Updated: 2026-11-16T15:46:27.000Z. Sources: 9. Developments: 2.

Municipalities in Brazil have initiated operations to remove irregular, abandoned, or unused cables from utility poles to improve urban safety and infrastructure maintenance.

In Cuiabá, the “Operação Telefone Sem Fio” is being conducted by city authorities and Energisa Mato Grosso. The initiative has removed approximately 55 tons of irregular wiring to date, including a recent action on Avenida do CPA where 400 meters of cabling were cleared from 15 poles. The operation is scheduled to continue through 2026 and 2027.

In Macaé, an operation coordinated by the Executive Secretariat of Public Services aims to remove nearly 100 kilometers of unused cables and accessories across six areas, including Centro and Imbetiba. Meanwhile, in Treviso, officials are developing a cooperation agreement with energy cooperatives and telecommunications companies to begin organized removal efforts in early 2027.

## Timeline

### 2026-11-16: Brazilian municipalities launch operations to remove abandoned cables

Macaé and Treviso are implementing measures to remove abandoned cables and reorganize aerial wiring to improve urban safety and infrastructure management.

2 sources. https://clstr.news/cluster/brazilian-municipalities-launch-operations-to-remove-abandoned-cables

### 2026-11-13: Cuiabá authorities conduct operation to remove irregular cables

Cuiabá authorities and Energisa Mato Grosso are removing irregular and unused cables from utility poles to improve safety and maintenance, an initiative expected to continue through 2027.

7 sources. https://clstr.news/cluster/cuiab-authorities-launch-operation-to-remove-irregular-cables

---