The reconstruction of the Kranjčevićeva Stadium in Zagreb has faced significant delays. Following a contract amendment between the City of Zagreb and the construction firm Strabag, the project completion date has been pushed from the end of 2025 to February 1, 2027.

The total project value has increased to approximately 47.69 million euros, including VAT. The amendment is attributed to the necessity for additional works, services, or goods not included in the original procurement. The stadium is intended to meet UEFA Category 4 standards and will feature 11,163 covered seats and ecological elements such as vertical gardens.

These delays impact NK Dinamo Zagreb, which planned to use the venue as a temporary home during the reconstruction of the Maksimir Stadium, creating planning challenges for the 2026/27 season. Recent reports confirm that Zagreb is extending the timeline for the new stadium construction into early 2027.

## Claims

- The estimated construction value of the Tivat market is 4,093,635 euros, including VAT. (corroborated by 2 sources)
- The contract for the preparation of the Main Project cost 66,499.72 euros. (corroborated by 2 sources)
- The planned complex includes an open-air market, a market space on the high ground floor, a multifunctional square, and two underground levels. (corroborated by 2 sources)
- The underground garage is designed to accommodate 66 parking spaces. (corroborated by 2 sources)
- The total gross construction area of the facility, including two underground floors, is 5,000 square meters. (corroborated by 2 sources)
- The expansion in Podgorač is largely funded by the Croatian Government through the National Recovery and Resilience Plan. (single source)
- The new school in Nova Gradiška will feature nine classrooms with cabinets, a dining room, and a library. (single source)
- The new school in Cavtat is described as an imposing object that meets all modern standards. (single source)
- The renovation of the Most na Soči gymnasium includes improved fire safety and new ventilation systems. (single source)

## Timeline

### 2026-08-29: Balkan region sees major investments in schools and sports infrastructure

Regional infrastructure projects across Croatia, Montenegro, Bosnia and Herzegovina, and Serbia are advancing, with major investments targeting new schools, sports halls, and stadium expansions.

63 sources. https://clstr.news/cluster/zagreb-stadium-reconstruction-delayed-until-2027

### 2026-08-29: Zagreb school renovation begins after six-year delay

Renovation of the ŠPUD school in Zagreb has finally begun after a six-year delay, with students expected to return to their original building by late 2027 or early 2028.

6 sources. https://clstr.news/cluster/zagreb-school-renovation-begins-after-six-year-delay

---
Cite as: Kranjčevićeva Stadium reconstruction delays. CLSTR, https://clstr.news/situations/kranjevieva-stadium-reconstruction-delays