# Morelia Teleférico construction progress

> Live situation record from CLSTR: https://clstr.news/situations/morelia-telefrico-construction-progress
> Updated: 2026-08-03T04:51:16.000Z. Sources: 4. Developments: 2.

In early July 2026 the Morelia cable‑car project was reported to have reached roughly 70 % of its overall construction work. By early August the effort moved into a critical stage: the installation of the main carrier‑tractor cable. The 50 mm galvanized steel strand, supplied by Swiss firm Fatzer, was laid to enable gondola movement. According to project lead María Elena Huerta, the first loop now has all 20 towers and a communications system in place, while the second loop still requires four towers between the Obelisco and Santa María stations. After the cable is spliced, the system will proceed to electromechanical testing.

## Timeline

### 2026-08-03: Morelia Teleférico Begins Cable Installation

The Teleférico de Morelia in Mexico has begun installing its high‑strength steel cable, made by Swiss firm Fatzer, a key step toward testing and full operation, announced Sedum chief María Elena Huerta.

4 sources. https://clstr.news/cluster/morelia-telefrico-begins-cable-installation

### 2026-07-06: Morelia, Mexico cable car project reaches 70% construction progress

Morelia's cable car project in Michoacán is 70% complete, with north‑loop cable linking four stations and electromechanical work starting at the zoo station; operation is slated for later this year.

2 sources. https://clstr.news/cluster/morelia-mexico-cable-car-project-reaches-70-construction-progress

---