# Poland nuclear plant construction advances

> Live situation record from CLSTR: https://clstr.news/situations/poland-nuclear-power-plant-development
> Updated: 2026-08-05T14:00:00.000Z. Sources: 32. Developments: 4.

In early July 2026 the Polish Sejm approved an amendment to the nuclear investment act creating a special category of building permits that allow early construction work on the country’s first nuclear facility before a full licence is issued. The law also defines safety and radiological approvals for those initial works, aiming to cut the project schedule by about two years. The amendment was subsequently adopted by the Senate and now awaits the president’s signature; work that affects nuclear safety still requires a separate authorization from the State Atomic Agency, which charges a 1.5 million zł fee and has nine months to assess applications. Domestic contractor ZBUD announced a multi‑million‑zloty investment to meet U.S. NQA‑1 quality standards so it can supply the Polar crane for reactor assembly and the Cask crane for spent‑fuel transport. ZBUD has been added to Westinghouse’s “Great Seven” list of potential domestic suppliers for the AP1000 reactors planned at the Choczewo site. The regional governor issued an early‑work permit enabling preparatory activities such as land leveling, temporary facilities, utility connections and deep geological surveys. In August 2026 the project’s main site‑preparation contract was signed: Polish builder Budimex received a 208.88 million zł award from Bechtel to carry out earth‑works, access roads, drainage and erosion control at Choczewo, with completion slated for 18 August 2028 and the first concrete pour planned for 2028. Shortly thereafter, Polskie Elektrownie Jądrowe transferred the 330‑hectare Choczewo site to U.S. contractor Bechtel, which will act as general contractor. Bechtel appointed Budimex to execute the earthworks, and over 330 ha of forested land have been cleared. Officials describe the effort as the largest investment in Poland’s modern economy and a strategic step toward energy security and diversification away from coal.

## Claims

- Budimex signed a contract to perform earthworks and site‑preparation for the plant. (corroborated by 7 sources)
- Polskie Elektrownie Jądrowe transferred the land for the first Polish nuclear power plant at Choczewo to Bechtel. (corroborated by 5 sources)
- Over 330 ha of forested land have been cleared and prepared for the project. (corroborated by 4 sources)
- The plant will consist of three Westinghouse AP1000 reactors with a total capacity of about 3.75 GW. (corroborated by 4 sources)
- Bechtel will act as the general contractor and manage the nuclear plant site. (corroborated by 3 sources)
- First concrete pour is scheduled for 2028 and the first block is expected to start commercial operation in 2036. (corroborated by 3 sources)
- The earthworks contract is valued at about 208.9 million PLN (≈ 49 million EUR). (corroborated by 2 sources)

## Timeline

### 2026-08-05: Polish nuclear plant construction advances as Bechtel takes site, Budimex begins earthworks

Polish nuclear plant site handed to Bechtel; Budimex starts earthworks on 330 ha, contract worth ~209 M PLN; three AP1000 reactors planned, first block to run by 2036.

9 sources. https://clstr.news/cluster/polands-first-nuclear-power-plant-groundwork-contract-signed-with-budimex

### 2026-07-23: Poland passes law to speed construction of its first nuclear power plant

Poland's parliament and senate approved a law allowing early construction work on its first nuclear plant, aiming to shorten the project timeline by two years and streamline permits.

7 sources. https://clstr.news/cluster/poland-passes-law-to-speed-construction-of-its-first-nuclear-power-plant

### 2026-07-11: Poland's nuclear plant project moves ahead as ZBUD gears up to supply specialist cranes

Poland's first nuclear plant gains a construction permit while ZBUD invests to become a certified supplier of specialist cranes for the project.

3 sources. https://clstr.news/cluster/polands-nuclear-plant-project-moves-ahead-as-zbud-gears-up-to-supply-specialist-cranes

### 2026-07-04: Polish Sejm approves law to speed up nuclear power plant investments

Poland's parliament passed a law enabling staged construction and earlier permits for nuclear plants while keeping strict safety oversight.

19 sources. https://clstr.news/cluster/polish-sejm-reviews-proposal-to-raise-first-pit-tax-threshold

---
Cite as: Poland nuclear plant construction advances. CLSTR, https://clstr.news/situations/poland-nuclear-power-plant-development