Quinbrook is advancing its Supernode battery energy storage system (BESS) project in Brendale, north of Brisbane. The project has reached significant development milestones, including the completion of Stage 2 commercial operations and achieving financial close on A$469 million in debt financing for Stage 3. 

Total financing for Stages 1, 2, and 3 is approximately A$1.2 billion. Once completed, the Supernode campus is expected to exceed 3 GWh in capacity, reaching 780MW / 3,074MWh. CATL is the core energy storage system supplier for the project. Located near the South Pine substation, the facility is intended to support the energy transition and infrastructure investment in Queensland.

## Timeline

### 2026-08-15: Quinbrook’s Supernode battery project reaches major milestones

Quinbrook’s Supernode battery storage project in Australia has completed Stage 2 operations and secured A$469 million for Stage 3, bringing total project financing to approximately A$1.2 billion.

8 sources. https://clstr.news/cluster/quinbrooks-supernode-battery-project-reaches-major-milestones

### 2026-08-02: Quinbrook proposes 520 MW battery at historic Uriarra Station near Canberra

Quinbrook Infrastructure seeks approval for a 520 MW battery on historic Uriarra Station near Canberra, covering ~10 % of the 1,200‑ha farm with minimal environmental impact and at least 2,100 MWh capacity.

2 sources. https://clstr.news/cluster/quinbrook-proposes-520-mw-battery-at-historic-uriarra-station-near-canberra

---