The Santa Catalina Photovoltaic Solar Park in Corrientes, Argentina, is entering its final construction stages. Developed by Coral Energía, a company under Grupo Corven, the 20 MW project covers 40 hectares and represents an investment of approximately US$ 13.3 million.

Construction is currently over 60% complete, employing a workforce that is 75% local residents. Energy generation is expected to begin in mid-October, with full commercial operation and grid connection scheduled for October 2026. This project is part of a broader expansion by Coral Energía that includes the Bella Vista Solar Park, which together aim to provide clean energy to more than 23,000 Argentine households.

## Timeline

### 2026-08-31: Santa Catalina Solar Park nears completion in Corrientes

The Santa Catalina Photovoltaic Solar Park in Corrientes, Argentina, is nearing completion with a 20 MW capacity and a US$ 13.3 million investment to boost renewable energy production.

4 sources. https://clstr.news/cluster/santa-catalina-solar-park-nears-completion-in-corrientes

### 2026-08-22: Mendoza Sur Solar Park project enters public hearing phase

Genneia SA is developing the Mendoza Sur Solar Park in Argentina, a 404 MW project that will be the largest photovoltaic facility in the country.

2 sources. https://clstr.news/cluster/mendoza-sur-solar-park-project-enters-public-hearing-phase

---