< Back to all clusters
[BUSINESS] · Nigeria · 10 sources

started · updated

Transmission Company of Nigeria disputes power outage claims

The Transmission Company of Nigeria (TCN) has issued several rebuttals against electricity distribution companies regarding recent power supply disruptions across the country.

In Abuja, TCN refuted claims by the Abuja Electricity Distribution Company (AEDC) that transmission line tripping from the Shiroro Transmission Substation caused a drop in power allocation from 641MW to 314MW. TCN stated the reduction was due to low generation on the national grid rather than line failures.

Regarding the Lekki area, TCN disputed reports from the Eko Electricity Distribution Company (EKEDP) concerning a transformer outage. TCN clarified that the disruption was caused by faults on EKEDP’s Oniru and Agungi 33kV feeders, which subsequently triggered the inter-tripping of TCN breakers.

Additionally, TCN dismissed allegations from Kaduna Electric regarding transmission constraints affecting power supply to Jos, asserting that all 330kV lines connected to the region remain in service.

Separately, TCN leadership has called for the establishment of special courts to fast-track the prosecution of individuals involved in the vandalism of critical energy infrastructure, noting that current theft charges do not reflect the severity of attacks on transmission towers and lines.

Entities

Abuja · Abuja Electricity Distribution Company · Eko Electricity Distribution Company · Kaduna Electric · National Control Centre · Nigeria · Shiroro Transmission Station · Transmission Company of Nigeria

Claims

What the coverage asserts, and how many sources carry each claim.

  • [DISPUTED] The reduction in power allocation was caused by low generation on the national grid rather than line tripping. tribuneonlineng.com
  • [○ 1 SOURCE] TCN described AEDC's claims regarding transmission line tripping as inaccurate and misleading. tribuneonlineng.com
  • [DISPUTED] Transmission lines from the Shiroro Transmission Station to Abuja have been tripping since Tuesday. realnewsmagazine.net
  • [○ 1 SOURCE] Available electricity supply to AEDC dropped from approximately 641 MW to 314 MW. realnewsmagazine.net
  • [○ 1 SOURCE] The reduction in electricity supply in Abuja is due to transmission constraints and low power generation. realnewsmagazine.net
  • [DISPUTED] All 330kV transmission lines within the Abuja region are currently in circuit. tribuneonlineng.com