started · updated
Akkuyu Nuclear Power Plant begins final tests on first unit
Final testing has commenced on the first power unit of the Akkuyu Nuclear Power Plant, constructed by the Russian State Nuclear Energy Corporation, Rosatom. Following permission from the Nuclear Regulatory Authority, the facility has entered the hot and cold commissioning phase.
During this stage, all equipment in the primary and secondary circuits will be tested under operating conditions before nuclear fuel is loaded. The reactor facility will be gradually heated, with the coolant in the primary circuit reaching nominal parameters of 285 degrees Celsius and 16.5 MPa of pressure. Tests will evaluate the strength of pipelines, vibration characteristics, electrical and safety systems, and reactor control mechanisms.
A key distinction of this phase is that fuel rod simulators are being used in the reactor instead of actual nuclear fuel. Once these tests and subsequent equipment revisions are successfully completed, the regulatory authority will permit the physical commissioning stage, which will involve the first loading of uranium fuel into the reactor.
Entities
Akkuyu Nuclear Power Plant · Aleksey Likhachev · Nuclear Regulatory Authority · Rosatom · Turkey