Akkuyu Nuclear Power Plant completes turbine foundation pour

Akkuyu Nuclear Power Plant has completed the concrete pouring for the turbine-generator foundation of its fourth power unit in Mersin, Turkey. This milestone marks the completion of turbine and generator foundation works for all four units of the plant.

The construction process involved the installation of 308 tons of reinforcement and 69 tons of embedded parts, including anchor equipment to secure the turbine unit. A continuous operation lasting over a day utilized nine concrete pumps to pour a total of 2,241 cubic meters of concrete.

The foundation is designed to support the weight of the equipment and distribute dynamic loads generated during operation. Special spring blocks will be used to reduce the transmission of vibrations to the machine hall structures. Following a 60-day curing period, the structure will undergo inspections by a commission including experts from the Turkish Nuclear Regulatory Authority and independent auditing bodies before equipment assembly begins.

Entities