Akkuyu Nuclear Power Plant control room ready for operation
A high-level management delegation led by Rosatom Director General Aleksey Likhachev visited the Akkuyu Nuclear Power Plant site in Mersin to inspect the progress of the first power unit.
Key developments include the completion of the first stage of hydraulic tests and the subsequent commissioning of the main circulation pumps. The facility's main control room is now reported as ready for operation, serving as the central hub for digital monitoring and decision-making processes.
Likhachev stated that the current objective is to complete the present stage as quickly as possible to enter the licensing process. The project aims to obtain an operating license and begin commissioning procedures by the end of the year. Technical preparations are currently focused on the cold stage of the reactor facility's cold-hot testing sequence.
Entities
Akkuyu Nuclear Power Plant · Akkuyu Nükleer A.Ş. · Aleksey Likhachev · Anton Dedusenko · Rosatom
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 4 SOURCES] Main circulation pumps have been commissioned following the completion of the first stage of hydraulic tests. cukurovagazetesi.com · enerjihaber.com · www.yeniyolgazetesi.com · haber.doviz.com
- [● 4 SOURCES] The goal is to complete the current stage, enter the licensing process, obtain an operating license, and begin commissioning by the end of the year. cukurovagazetesi.com · enerjihaber.com · www.yeniyolgazetesi.com · haber.doviz.com
- [● 4 SOURCES] Work is ongoing to prepare equipment and systems for the cold stage of the reactor facility's cold-hot tests. cukurovagazetesi.com · enerjihaber.com · www.yeniyolgazetesi.com · haber.doviz.com
- [● 4 SOURCES] The main control room for the first power unit of the Akkuyu Nuclear Power Plant is ready for operation. cukurovagazetesi.com · enerjihaber.com · www.yeniyolgazetesi.com · haber.doviz.com