started · updated
Australia's Regional Renewable Projects Hit Financing Roadblocks
Only 788 MW of the 12.9 GW of wind capacity earmarked under the Australian government's Capacity Investment Scheme (CIS) has reached financial close, revealing a financing squeeze for large‑scale renewable projects in regional Australia. The Albanese government relies on the CIS to meet its target of 82 % renewable electricity in the grid by 2030, but stakeholders cite transmission limits, planning delays and project economics as barriers.
A Clean Energy Council report shows new utility‑scale wind and solar commitments fell 46 % in 2025, with just 2.3 GW reaching financial commitment, prompting chief executive Jackie Trad to call the sector a "critical juncture" and warn that investment is at a decade low.
Entities
Albanese government · Australia · Capacity Investment Scheme · Clean Energy Council · Jackie Trad