Bac Ninh road project accelerates following land clearance

Construction on the DT287 road upgrade and expansion project in Bac Ninh province has accelerated following the resolution of long-standing land clearance issues. The project, which spans from Dai Dong commune to the intersection north of Kinh Duong Vuong bridge, aims to be completed before the New Year holiday.

Local authorities and the project management board reported that land disputes at the Phat Tich gas station and the Noi Due - Tri Phuong intersection have been resolved through community mobilization. As of early September, the project has reached 65% of its total workload. Contractors have deployed over 100 pieces of equipment and workers to meet the deadline of December 31, 2026.