Bau-Kuching road upgrade project projected for 2028
Construction on a proposed RM1.5 billion road upgrading project linking Bau to Kuching could begin in 2028, according to Dato’ Ir. Lo Khere Chiang. The timeline is subject to the completion of planning, approvals, and funding processes.
The project involves upgrading and widening a 25 km stretch across three phases. Phase 1, estimated at RM500 million, involves widening the road from Bau to Keranji into a four-lane carriageway and is currently in the design stage. Phase 2, also estimated at RM500 million, covers the stretch from Keranji to Jalan Stephen Yong and includes the construction of a new two-lane bridge alongside the existing Batu Kitang Bridge.
Phase 3 will address the remaining section between Jalan Stephen Yong and the Mile 7 traffic lights. This final phase faces engineering and logistical challenges due to the presence of major water pumping mains, electrical cables, and telecommunications infrastructure that require relocation or protection.
Entities
Bau · Kuching · Lo Khere Chiang · Public Works Department · Sarawak United Peoples’ Party