Brazil TCU authorizes Transnordestina railway works in Pernambuco
The Brazilian Federal Court of Accounts (TCU) has authorized the resumption of construction for the Transnordestina Railway on the stretch connecting Salgueiro to the Port of Suape in Pernambuco. The decision, reached during a judgment on a request for re-examination by the Attorney General's Office (AGU), allows physical works to proceed without waiting for the completion of supplementary socioeconomic viability studies.
Relator Benjamin Zymler argued that since approximately 35% of the project is already executed, the costs of a new interruption justify the release of works. He proposed that technical studies be conducted in parallel with construction to avoid further delays. The decision was supported by most ministers, though Jhonatan de Jesus dissented, maintaining that the suspension should remain until economic advantages are fully demonstrated.
The Pernambuco section of the railway spans approximately 544 kilometers. The project had faced over a decade of paralysis, particularly after the concessionaire Transnordestina Logística S.A. returned the Pernambuco branch to the Union in 2022. The resumption is part of the New Growth Acceleration Program (PAC), with Infra S.A. tasked with managing the construction.
Entities
Advocacia-Geral da União · Benjamin Zymler · Infra S.A. · Pernambuco · Transnordestina Railway · Tribunal de Contas da União