The first phase of the Cameroon-Chad Power Interconnection Project (PIRECT) has been restructured following a CFA287 billion funding shortfall. The revised cost for the initial phase on the Cameroonian side is estimated at approximately CFA145.2 billion, or €221.3 million.

An assessment mission by the African Development Bank (AfDB) in October 2026 determined that the scaled-back plan, referred to as Option 2-bis, will focus on the cross-border component. The project aims to enable the export of 100 megawatts of electricity to Chad by 2030.

Proposed infrastructure includes 426 kilometers of 225-kilovolt high-voltage transmission lines along the Wouro-Soua–Garoua II and Maroua–Chad border routes. The plan also involves constructing a new substation at Garoua II and extending existing substations at Wouro-Soua in the Adamawa region and Maroua in the Far North region.

Electricity trade is expected to involve Cameroon's utility, Socadel, and Chad's ChadElec, under the technical supervision of Sonatrel. The project management unit also intends to integrate resettlement action plans and environmental and social management measures into the AfDB financing arrangements.

Entities

African Development Bank · Cameroon · Chad · SOCADEL · Sonatrel