Chau Doc - Can Tho - Soc Trang expressway faces material shortages

Construction of components 2, 3, and 4 of the Chau Doc - Can Tho - Soc Trang expressway is facing significant delays due to a shortage of construction materials. Specifically, there is a deficit of over 2.6 million cubic meters of stone required for the projects.

In addition to the stone shortage, sand supplies are also problematic. While 11.89 million cubic meters of sand have been delivered out of a total demand of 16.64 million cubic meters, approximately 5 million cubic meters remain difficult to secure. Challenges include expired mining licenses in Vinh Long province and pending permit procedures for several mines in Can Tho.

Contractors have reported that actual material and transportation costs are significantly higher than original estimates, exacerbated by rising fuel prices. The Can Tho Department of Transport and Agriculture is currently working with authorities in Vinh Long and An Giang provinces to resolve these supply issues and expedite licensing to maintain project progress.

Entities

An Giang Province · Can Tho People's Committee · Chau Doc - Can Tho - Soc Trang Expressway · Vĩnh Long province