Chodov building reconstruction progressing faster than expected

The reconstruction of the firefighters and guards building in Chodov is progressing faster than expected. Although construction revealed unforeseen issues with floor and ceiling structures due to varying materials, Mayor Patrik Pizinger stated that these changes have not impacted the completion deadline.

The total cost, including additional works, is expected to reach approximately 38 million CZK, which remains within the city's original budget. The project is scheduled for completion in January 2027, with the building handover planned for early February. Volunteer firefighters and municipal guards are expected to move back into the facility gradually during the spring of 2027.