Ciudad Juárez advances 90% on 300 million peso police park
Construction of the Parque Club Guardianes Juárez in the Parajes de Oriente neighborhood has surpassed 90% completion. The project represents a joint investment of 300 million pesos between the municipal government and the Trust for Competitiveness and Citizen Security (Ficosec), with the city also providing the land.
Designed for approximately 2,800 members of the Municipal Police, Road Safety, Firefighters, and Civil Protection, the complex can accommodate 1,500 people simultaneously. Facilities include swimming pools, a children's splash pad, a gym, a sauna, padel, racquetball, football, and basketball courts, as well as areas for boxing and taekwondo.
Officials noted that the initial 260 million peso budget increased to 300 million pesos to include additional equipment, such as solar panels to reduce energy costs. Due to rain-related delays in paving and waterproofing, the park is expected to begin operations within 30 to 45 days.
Entities
Ciudad Juárez · César Omar Muñoz Morales · Ficosec · Héctor Rafael Ortiz Orpinel · Parque Club Guardianes Juárez · Raúl de León Apráez
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 3 SOURCES] The Parque Club Guardianes Juárez construction has exceeded 90% progress. frontenet.com · circuitofrontera.com
- [○ 1 SOURCE] The park is intended for approximately 2,800 security and emergency personnel and their families. circuitofrontera.com
- [● 3 SOURCES] The project involves a joint investment of 300 million pesos. frontenet.com · circuitofrontera.com
- [● 2 SOURCES] The facility has a simultaneous capacity of approximately 1,500 people. circuitofrontera.com
- [● 2 SOURCES] The initial investment was 260 million pesos before increasing to 300 million pesos. frontenet.com · circuitofrontera.com
- [● 2 SOURCES] The park is expected to begin operations within 30 to 45 days. frontenet.com · circuitofrontera.com
- [● 3 SOURCES] The total investment for the project is 300 million pesos. frontenet.com · circuitofrontera.com
- [○ 1 SOURCE] Solar panels were added to the project to reduce electricity costs. frontenet.com
- [○ 1 SOURCE] Rain caused a delay of approximately one and a half months in paving and waterproofing works. frontenet.com