Clube do Remo advances construction on CT Rei da Amazônia
Construction is progressing on the CT Rei da Amazônia, a new training center for Clube do Remo located in the Outeiro district of Belém. The project involves an investment exceeding R$ 15 million, with more than R$ 5 million being funded directly by the club.
Work is currently underway on several fronts, including drainage and earthmoving for the official fields. Specifically, drainage systems are being installed on the first field, while earthmoving is nearing completion on the second and third fields. Work has also begun on the fourth field.
In the area designated for the main building, crews are performing mechanized soil compaction and filling, and the concreting of the floor slab has commenced. Additionally, the entrance portico is in the final stages of execution, and internal work on the gatehouse has been completed. The complex is being built in three stages to serve both professional football and youth categories, with an expected completion date of February 2027.