Contraloría finds premature deterioration in Huanchaco road project
The Comptroller General of the Republic has reported premature deterioration of asphalt pavement in the Las Lomas settlement within the Huanchaco district, Trujillo province. The roadwork project, titled “Creación de transitabilidad vial en las calles del asentamiento humano Las Lomas,” had a budget of S/ 9,295,156.61.
The project was awarded to Consorcio Vial OTG in March 2025, with the contract signed in April 2025. Although the work was officially received on February 9, 2026, a concurrent control service conducted by the Comptroller in October 2026 identified significant issues.
Specific damages include fatigue cracking, also known as “crocodile skin,” on Avenida Santo Toribio and San Pedro Street. These findings were documented in municipal reports prior to the Comptroller's inspection, noting that the pavement is failing prematurely.