Cuba energy crisis worsens as major thermoelectric plants fail

Cuba is facing a deepening energy crisis as major thermoelectric plants experience technical failures. The Antonio Guiteras plant, the nation's largest, briefly rejoined the National Electroenergetic System (SEN) on Sunday, contributing 150 MW. However, its return was short-lived; the plant disconnected again late Sunday night due to a leak in the burner front wall.

Simultaneously, the Carlos Manuel de Céspedes plant in Cienfuegos went offline because of a steam leak in a high-pressure heater. This failure occurred just days after the unit had been reconnected. The Unión Eléctrica (UNE) reported a severe power deficit, noting that at 6:00 am, system availability was only 1,240 MW against a demand of 2,750 MW. Forecasts indicated a peak demand deficit of up to 1,840 MW, leading to widespread and massive power outages across the country.

The instability follows a major collapse of the national electrical grid on September 18, which caused extensive damage to boiler economizers and other critical components in several plants.

Entities

Antonio Guiteras Thermoelectric Plant · Antonio Guiteras Thermoelectric Power Plant · Carlos Manuel de Céspedes Thermoelectric Plant · Carlos Manuel de Céspedes Thermoelectric Power Plant · Cuba · Matanzas · Román Pérez Castañeda · Unión Eléctrica

Claims

What the coverage asserts, and how many sources carry each claim.