Cuba faces extreme power outages as major thermal plants fail
Cuba is experiencing a severe energy crisis following the failure of critical generation units. The Antonio Guiteras Thermal Power Plant (CTE) has taken Unit 1 out of service due to a leak in the economizer, forcing the national electrical system into a state described as “máximo apagable” (maximum load shedding).
This critical state means provincial companies have reached the upper limit of electrical demand they can disconnect to prevent a total grid collapse. Consequently, non-essential circuits remain disconnected almost continuously, leaving only indispensable services like hospitals and water pumping stations with power. In provinces such as Matanzas, some areas have reported continuous outages exceeding 72 hours.
To address the shortage, technical brigades have begun intervening in the generation turbine of the Lidio Ramón Pérez Thermal Power Plant in Felton. This maintenance operation, involving specialized teams from Holguín, is expected to last approximately 20 days with 24-hour work shifts. The Lidio Ramón Pérez plant is considered a vital pillar of the national electrical system alongside the Guiteras plant.
Entities
Antonio Guiteras Thermal Power Plant · Cuba · Lidio Ramón Pérez Thermal Power Plant · Matanzas · National Electrical System