Cuiabá infrastructure works in Residencial Coxipó reach 44.75% completion
Infrastructure works in the Residencial Coxipó neighborhood of Cuiabá have reached 44.75% completion. The third stage of the project has finished the first phase, which included rainwater drainage and paving for streets 10, 11, 12, 13, and 14, as well as sections of Avenues F and A.
The comprehensive project covers 18 roads and includes earthmoving, drainage, and accessibility services. While paving is complete on several streets, additional work such as curbs, gutters, accessible sidewalks, and signage is still required.
The next phase of work will focus on earthmoving for various streets, including Rua 14, Avenida F, and several others. The current phase is expected to be completed by December 27, 2026, with the full delivery of the third stage scheduled for the second half of 2027. The project also aims to create a new road connection between Residencial Coxipó and the Santa Teresinha neighborhood via Avenue A to improve local mobility.