Dong Thap accelerates Provincial Road 857 construction

Construction on Provincial Road 857, specifically the section between National Highway 30 and Provincial Road 845 in Dong Thap, is accelerating. After facing previous delays due to shortages in materials, site clearance, and technical infrastructure, the project has entered a high-speed phase.

Nearly 100 engineers and workers, along with over 100 pieces of machinery, have been mobilized to maintain progress through the September 2 National Day holiday. At package number 13, managed by Tuan Hien Co., Ltd, the project has reached approximately 86% completion, with a target to finish by September 30, 2026. Meanwhile, at package number 15, managed by Thanh An 96 Construction Joint Stock Company, workers are working extended hours to meet project goals.