Duke Energy Florida proposes 300 MW solar expansion
Duke Energy Florida has filed plans with the Florida Public Service Commission to construct four new solar sites in Orange and Sumter counties. The expansion aims to add 300 megawatts of capacity to the state grid, with all projects targeted for completion by mid-2028.
The initiative is projected to generate approximately $1 billion in customer savings over the operational lifetimes of the sites, which are expected to run for about 30 years. These savings are anticipated to stem from avoided fuel costs and federal tax credit transfers, with each site projected to save roughly $250 million in displaced fuel costs.
The proposal comes as Florida continues to experience rapid population growth and rising electricity demand. Duke Energy Florida currently operates 25 solar sites providing 1,850 MW to the grid.
Entities