Durrës reconstruction funds mismanaged, state audit finds
A final report from the Supreme State Control (KLSH) regarding the activities of the Durrës Municipality for the 2023–2024 period has revealed significant irregularities in the management of emergency and reconstruction funds following the 2019 earthquake.
The audit focuses on two limited procurement procedures conducted in July 2024 to reinforce damaged buildings. With a combined limit fund of 447.7 million lek (approximately 4.5 million euros), both contracts were awarded on August 28, 2024, to the same operator consortium: Rajli Ndërtim and G. P. G. Company.
According to the report, the winning bids were suspiciously close to the maximum limits: 99.76% for the “Big Kristi” building and 99.75% for the buildings on Pelikan Street, resulting in a public budget saving of less than 0.25%. The KLSH concluded that this lack of economic efficiency resulted from a deformed evaluation process. The audit noted that the same three officials served on the evaluation commission for both procedures and that several legitimate competitors were disqualified based on unfounded arguments or errors, while the winning companies were allegedly permitted to overlook fundamental violations.
Entities
Durrës · Durrës Municipality · G. P. G. Company · Rajli Ndërtim · Supreme State Control