Dominican Republic advances major electricity infrastructure upgrades
The National Health Service will begin the first phase of a major renovation at Hospital Salvador B. Gautier next week, expanding the emergency department and adding a magnetic resonance scanner and angiography‑CT equipment to improve diagnostic capacity.
The Electric Transmission Company (ETED) will complete the final stage of a 69 kV transmission line reconduction between Puerto Plata I and II, boosting line capacity and reinforcing system reliability across the northern province.
Edenorte has repowered the Montecristi sub‑station with a new 16‑20 MVA transformer, temporarily interrupting service to several neighborhoods while increasing supply stability for residential, commercial and industrial customers.
Edesur has launched a RD$1.9 billion “Program of Polygon Recovery” covering 11 provinces, installing over 260 km of medium‑voltage distribution lines, anti‑fraud meters and tele‑measurement technology to normalise service for tens of thousands of users.
The Eastern Electricity Company (Edeeste) finished upgrades to the power supply for the athlete village of the 2026 Central American and Caribbean Games, installing a dedicated circuit and a standby circuit to guarantee uninterrupted electricity for the event.