Electrical grid upgrades are concluding in the areas of Vitiana, Pagnana, and Avane following a series of interventions aimed at resolving local service disruptions. The project involves the complete reconstruction of the 'Manetti' medium-voltage power line.
Technicians have replaced approximately 1.5 km of overhead conductors with modern pre-formed cables and installed new generation equipment along the backbone. To finalize the technical closure and commission the new network configuration, E-Distribuzione has scheduled temporary service interruptions on October 1 and 2. These outages, occurring during daylight hours, will affect specific residential streets to minimize community impact.