EVNNPT to invest 923 billion VND in 220 kV Mo Cay - My Tho power line

The National Power Transmission Corporation (EVNNPT) has been approved as the investor for the 220 kV Mo Cay – My Tho transmission line project. The project, with a total investment exceeding 923 billion VND, is expected to be completed by the end of 2028.

The 36.23 km project will consist of two overhead circuits connecting the Mo Cay 220 kV substation to the My Tho 500/220 kV substation. Approximately 25.37 km of the line will pass through Vinh Long province, while 10.86 km will traverse Dong Thap province. The project aims to transmit renewable energy, such as wind and solar power, from the Southwest region into the national grid, reduce power losses, and enhance grid stability for Vinh Long and Dong Thap.

Operational reports from September 2026 indicate that certain power lines in the My Tho area have reached warning levels, operating at 90-100% of their rated capacity due to high power generation and increasing demand. The new project is intended to alleviate this load pressure and improve voltage quality.

Entities

Dong Thap · Mo Cay · Mỹ Tho · National Power Transmission Corporation · Vinh Long Provincial People's Committee

Claims

What the coverage asserts, and how many sources carry each claim.