Flamanville EPR reactor shuts down to replace defective vessel lid

The Flamanville EPR nuclear reactor in Normandy has been shut down for a 350-day maintenance period. A primary objective of this shutdown is the replacement of the reactor pressure vessel lid.

The 100-ton steel component, measuring approximately six meters in diameter, was originally forged at the Creusot facilities. The replacement was mandated by the French Nuclear Safety Authority (ASN) due to a defect discovered in 2014. The original lid contained excessive carbon concentrations in the steel, which posed a risk regarding its ability to resist crack propagation.

Following the replacement, the defective lid will be stored on-site for two years in a dedicated facility before being transported to a radioactive waste storage center managed by Andra. This maintenance occurs less than two years after the EPR's initial connection to the power grid.

Entities

Autorité de sûreté nucléaire et de radioprotection · EDF · Framatome