Galician High Court upholds Serra do Faro wind farm legality
The High Court of Justice of Galicia (TSXG) has dismissed an appeal by the environmental association Petón do Lobo against the Serra do Faro wind farm expansion project. The court confirmed the legality of the Xunta de Galicia's decision to declare the project of public utility, a necessary step for land expropriation.
The project, promoted by Pena da Costa Eólica, S.L., is located across the municipalities of Rodeiro, Dozón, San Cristovo de Cea, and Piñor. While the environmental group argued that the project's construction authorization was under precautionary suspension, the court ruled that the suspension only affected the physical execution of works, not the validity of the administrative act.
The court also declined to evaluate claims regarding environmental impact assessments, potential damage to birdlife, or impacts on cultural heritage, stating these issues exceeded the scope of the current proceedings.
Entities
High Court of Justice of Galicia · Pena da Costa Eólica, S.L. · Petón do Lobo · Serra do Faro · Xunta de Galicia