started · updated
Gandara Bridge girders collapse attributed to human error
Two concrete girders collapsed at the P512-million Gandara Parallel Bridge construction site in Samar on Tuesday, November 17. The Department of Public Works and Highways (DPWH) reported that the incident occurred on the Maharlika Highway while a roller attachment was being removed.
Public Works Secretary Giovanni Lopez stated that initial findings attribute the collapse to human error rather than design flaws. According to Lopez, a contractor’s crane operator removed the roller attachment without authorization from the DPWH or the project engineer, causing the girders to fall. No workers or bystanders were injured in the incident.
The contractor has accepted full responsibility and committed to replacing the damaged girders at no additional cost to the government. Replacement work commenced on Wednesday night, and officials expect the project to face a delay of only one to two days under a catch-up plan.
Entities
Department of Public Works and Highways · Gandara Parallel Bridge · Giovanni Lopez · Maharlika Highway · Samar