Grava school complex faces two-week heating delay
More than 4,000 students at the Grava school complex in Athens are facing at least two more weeks without heating. The delay follows the discovery that existing natural gas pipes were unsuitable and did not meet required specifications, necessitating a full replacement of the network.
Repair work is currently underway at the complex's boiler room, including the installation of a protective chimney cover and lightning rods. The situation is causing significant concern among parents and educators, especially as temperatures in Athens are forecasted to drop to between 7 and 8 degrees Celsius in the coming week.
Deputy mayors for Technical Services and Education of the Municipality of Athens have left the possibility open for a return to remote learning if the low temperatures make in-person classes impossible. Some parents are reportedly considering purchasing individual heaters at their own expense to ensure better conditions for students until repairs are completed.