Greece targets March 2027 for Drama–Amphipoli highway contract

The Greek Ministry of Infrastructure and Transport has set March 2027 as the target date for signing the contract for the Drama–Amphipoli highway. Deputy Minister Nikos Tachiaos announced the timeline in Parliament, noting that the project has entered the contracting phase.

GEK TERNA has been named the provisional contractor and has already submitted a guarantee letter of 8 million euros. The next steps involve the submission of necessary documentation, details regarding an independent auditor, verification of the financing model, and the finalization of contractual documents.

The 43-kilometer project, with a budget of 248.5 million euros including VAT, will be implemented as a Public-Private Partnership (PPP). It includes the Paleokomi–Mavrolefki and Mavrolefki–Drama sections, featuring nine interchanges and a mix of new construction and upgrades to existing roads. The project is expected to have a three-year construction period within a 30-year contract duration.

Additionally, approximately 18.5 million euros has been allocated for land expropriations, with nine land registries currently in progress for the first section of the project.

Entities

Amphipoli · Drama · GEK TERNA · Ministry of Infrastructure and Transport · Nikos Tachiaos