Havlíčkův Brod bridge project to support Dukovany nuclear plant transport
Construction of a new bridge in Havlíčkův Brod has entered the foundation stage, with more than 70 large‑diameter pilot piles being drilled into stable geological layers. The works, overseen by the Road and Motorway Directorate (ŘSD), will require roughly 150–200 fully loaded concrete mixer trucks for the foundation concrete.
The bridge is being built to carry loads up to 900 tonnes, enabling the transport of oversized components for the Dukovany nuclear power plant. The project’s cost exceeds 158 million Czech crowns (excluding VAT). Demolition of the old bridge was completed by mid‑May, and about 2,500 tonnes of concrete rubble were removed in June. First traffic over the new structure is expected in the second half of the next year.
Strabag is the general contractor responsible for the construction.
Entities: Dukovany Nuclear Power Plant · Havlíčkův Brod · Luděk Hubáček · Road and Motorway Directorate (ŘSD) · Strabag
Claims
What the coverage asserts, and how well corroborated each claim is across sources.
- [○ 1 SOURCE] Construction cost exceeds 158 million Czech crowns, excluding VAT. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))
- [○ 1 SOURCE] Demolition of the old bridge was completed by mid‑May, and about 2,500 tonnes of concrete rubble were removed in June. (Edita Novotná, spokesperson for construction firm Strabag)
- [○ 1 SOURCE] The bridge will be capable of carrying loads up to 900 tonnes. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))
- [○ 1 SOURCE] Strabag is the general contractor for the bridge project. (Edita Novotná, spokesperson for construction firm Strabag)
- [○ 1 SOURCE] More than 70 large‑diameter pilot piles are being drilled for the new bridge in Havlíčkův Brod. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))
- [○ 1 SOURCE] Approximately 150–200 fully loaded concrete mixer trucks will be needed for the foundation concrete. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))
- [○ 1 SOURCE] First traffic over the bridge is expected in the second half of the next year. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))
- [○ 1 SOURCE] The bridge is intended to support transport of oversized loads for the Dukovany nuclear power plant. (Luděk Hubáček, regional spokesperson for the Road and Motorway Directorate (ŘSD))