Havlíčkův Brod gas pipeline reconstruction to cause traffic disruptions

Gas pipeline reconstruction in Havlíčkův Brod will cause traffic and pedestrian disruptions from September 1 to October 9. The project, managed by Kubík s. r. o., will be carried out in three stages.

During the first stage (September 1–11), sidewalks on Ledečská and Stamicova streets will be closed. The second stage (September 15–25) will affect the intersection of Nerudova and Ledečská streets and will impact public transport, as bus lines 1 and 11 will no longer serve the Havlíčkův Brod Hospital stop. The final stage (September 29–October 9) involves sidewalk closures on Ledečská street between house numbers 2597 and 2735.

Motorists will face partial road closures in each stage, with traffic managed via shuttle signals. Drivers are advised to expect delays, particularly during peak hours.