Ho Chi Minh City canal renovation projects face delays

Major canal and waterway renovation projects in Ho Chi Minh City are experiencing various delays due to land clearance issues and rising material costs.

The Tham Luong - Ben Cat - Nuoc Len canal project, with a total investment of over 9,030 billion VND, has reached approximately 75% completion. However, several construction packages are behind schedule. Challenges include pending land handover in Binh Loi Trung ward and increased costs for construction materials, such as a 40% rise in asphalt prices.

Simultaneously, the Xuyen Tam canal and North Doi canal bank renovation projects are underway. The Xuyen Tam project, costing over 17,200 billion VND, involves three main construction packages with varying progress levels. While some sections are expected to be completed by 2026, the project faces hurdles regarding technical infrastructure relocation and land handover involving Tan Thuan Construction Investment Co., Ltd.