Honduras audit reveals failure of energy loss reduction program
An audit by the Tribunal Superior de Cuentas (TSC) has criticized the management of Honduras’ National Program for Loss Reduction (PNRP). Despite executing L5,644.7 million between 2022 and 2024, the program failed to meet its primary objectives regarding the reduction of technical and non-technical losses for the National Electric Energy Company (ENEE).
The report highlights significant inefficiencies, particularly in 2023, when the program executed only 43.57% of its planned actions. During that year, energy recovery reached only 25.34% of the projected 380.48 million kilowatt-hours (kWh). While 2024 showed improvements with a 70.72% execution rate of planned actions and 61.35% of the energy recovery goal, the TSC noted that administrative and financial deficiencies persist.