Iernut power plant nearing completion to boost Romania's energy grid
The Iernut gas-fired power plant in Romania is nearing completion, with Romgaz aiming to bring the facility into operation by the end of this year. Prime Minister Ilie Bolojan announced that the plant is expected to undergo testing during the winter and reach full operational capacity in the first quarter of next year.
The project, which began in 2016, has faced significant delays of approximately seven years due to management issues, the pandemic, and the bankruptcy of the original Spanish general contractor, Duro Felguera. Romgaz took over direct administration of the project after it reached roughly 90% completion. Currently, the project is reported to be at a 98% completion stage.
Once operational, the plant will add 430 MW of capacity to the national energy system. This is intended to address production deficits in central and western Romania while reducing pressure on the Transelectrica transport networks by balancing the surplus in the southeast. Romgaz CEO Răzvan Popescu stated that the goal is to synchronize the plant with the national grid as soon as possible to ensure economic recovery of the investment.
Entities
Duro Felguera · Iernut · Ilie Bolojan · Romgaz · Răzvan Popescu
Claims
What the coverage asserts, and how many sources carry each claim.
- [● 2 SOURCES] The plant is scheduled to operate at full capacity in the first quarter of next year. energymagazine.ro · www.radiomures.ro
- [○ 1 SOURCE] The project is currently at a 98% completion stage. financiarul.ro
- [● 2 SOURCES] The plant will undergo testing during the winter period. energymagazine.ro · www.radiomures.ro
- [● 2 SOURCES] Romgaz took over the project after the bankruptcy of the Spanish general contractor, Duro Felguera. www.radiomures.ro · financiarul.ro
- [○ 1 SOURCE] The project has faced delays of approximately seven years since its original 2019 completion target. financiarul.ro
- [● 2 SOURCES] The plant will help balance the national energy system by reducing pressure on east-west transport networks. energymagazine.ro · www.radiomures.ro
- [○ 1 SOURCE] The plant will provide 430 MW of capacity to the national grid. financiarul.ro
- [● 2 SOURCES] The Iernut power plant is expected to be completed by the end of this year. energymagazine.ro · www.radiomures.ro