Infrastructure projects advance in Puerto Natales and Escobar
In Puerto Natales, construction of the new Rubens Bridge on Route 9 has reached 74.77 percent progress. The project involves building a 105 meter long bridge consisting of three 35 meter spans, alongside improvements to approximately 4 kilometers of access roads. Authorities noted that the work is ahead of schedule, with projections suggesting completion by April 2027, well before the contractual deadline of September 2027.
In Escobar, Argentina, work is underway on a new road distributor and sidewalks along Route 25. Funded by private developers including Consultatio S.A., the project requires an investment of approximately 2,000 million pesos and is currently 30 percent complete. The infrastructure aims to improve safety for residents and workers traveling toward Paraná de las Palmas, featuring LED lighting, bus shelters, and improved drainage.