Integration Bridge access works face cost increases and delays

The completion of access roads to the Integration Bridge on the Paraguayan side is facing significant delays and rising costs. Data from the Paraguayan Ministry of Public Works and Communications (MOPC) indicates that the project's cost has increased by 15.23%, rising from approximately G. 804.2 billion to G. 926.7 billion.

While the bridge itself has been ready since August 2023, full operation depends on the completion of several infrastructure lots. Current projections suggest the following timelines:

• Rural Access Lot 2: 99% complete, expected finish in November 2026. • Rural Access Lot 1: 85% complete, expected finish in February 2027. • Bridge over the Monday River: 45% complete, expected finish in April 2027.

If construction continues according to these planned conditions, the new international connection between Foz do Iguaçu and Presidente Franco may only be fully operational in the second half of 2027.