JR Central faces delays in Maglev construction due to compensation and bid-rigging issues
JR Central is facing multiple setbacks regarding the construction of the Chuo Shinkansen Maglev line. In Takagi Village, the company has announced a policy to provide compensation to residents affected by sunlight issues caused by elevated tracks before construction is completed in March 2029.
Simultaneously, progress in the Shizuoka section has been halted following a bid-rigging scandal. Major construction firms Taisei Corporation and Kajima Corporation received guilty verdicts and are subject to a 120-day business suspension from November 7 through March 6. This suspension prevents any contract negotiations with JR Central during this period, delaying the start of tunnel excavation and complicating the timeline for the Nagoya-to-Shinagawa service.