Korea Zinc has received approval from the Tennessee Valley Authority (TVA) to secure a large-scale power supply for its Project Crucible, a massive integrated smelting facility in Tennessee, USA. The TVA board approved a power contract capacity of 230MW, with electricity supply scheduled to begin in 2029.

Project Crucible involves an investment of approximately $7.4 billion to produce 12 types of non-ferrous metals, including 11 critical minerals designated by the US government, and sulfuric acid for semiconductors. The project has already achieved several regulatory milestones, including inclusion in the federal FAST-41 expedited permitting process and passing the final environmental assessment with a finding of no significant impact.

Construction is slated to begin in 2027, with commercial production of some products expected by 2029. The project is anticipated to create more than 400 new jobs in the state of Tennessee.

Entities

Choi Yun-beom · Korea Zinc · Project Crucible · Tennessee · Tennessee Valley Authority