Maksimir stadium competition faces appeals and political scrutiny

The international architectural competition for the new Maksimir stadium in Zagreb has faced significant controversy following the selection of the Milan-based VG13 Architects Studio Associato. The winning design has drawn widespread criticism from fans and the public, primarily due to concerns regarding its functionality and the lack of connected stands.

Croatian Prime Minister Andrej Plenković expressed personal dissatisfaction with the selected design and suggested investigating legal avenues to potentially cancel the tender and launch a new one. Zagreb Mayor Tomislav Tomašević noted that while the professional jury supported the decision, the city and the government must find a solution that satisfies both experts and the stadium's primary users, the fans.

Two formal appeals have been filed with the State Commission for Control of Public Procurement Procedures (DKOM). Mayor Tomašević indicated that all options remain open, but the city must wait for the legal appeal period to expire before making further decisions regarding the project's future.

Entities

Andrej Plenković · City of Zagreb · Dinamo Zagreb · GNK Dinamo · GNK Dinamo Zagreb · Kranjčevićeva Stadium · Maksimir Stadium · Nezir Pivić · Sirrah · Strabag · Tomislav Tomašević · UEFA

Claims

What the coverage asserts, and how many sources carry each claim.

  • [○ 1 SOURCE] Strabag is the contractor for the works valued at approximately 47.5 million euros including VAT. www.monitor.hr
  • [● 2 SOURCES] The architectural firm Sirrah released new renderings of the Kranjčevićeva stadium reconstruction.
  • [● 2 SOURCES] Seats will be colored in a combination of black, grey, and white.
  • [● 2 SOURCES] The pitch dimensions will be 105 by 68 meters.
  • [● 3 SOURCES] The stadium will meet UEFA Category 4 requirements. www.monitor.hr
  • [DISPUTED] The new stadium will have 11,163 seats. www.monitor.hr
  • [● 2 SOURCES] The project includes a new city square of approximately 6,300 square meters and over 400 parking spaces.
  • [● 2 SOURCES] The stadium will feature four separate, fully covered stands.
  • [○ 1 SOURCE] Strabag is the contractor for the Kranjčevićeva stadium works, valued at approximately 47.5 million euros including VAT. www.monitor.hr
  • [● 5 SOURCES] The Prime Minister suggested investigating legal possibilities to cancel the current tender and launch a new one. biznis.rs · hrvatska-danas.com · golazo.ro
  • [○ 1 SOURCE] Independent auditor Boris Vranješ stated that the winning design's load-bearing structure is insufficiently developed and technically questionable. www.vecernji.ba
  • [● 2 SOURCES] The construction cost of the new Maksimir stadium is estimated to be between 175 and 200 million euros. sportsport.ba