started · updated
Krosno County to invest 2.1 million PLN in bridge reconstruction
Krosno County is proceeding with the modernization of county road nr 2112R, connecting Królik Polski and Bałucianka. An agreement was signed on August 28, 2026, for the reconstruction of bridge nr JNI 01015474 and its access roads. This marks the third bridge on this specific route to undergo modernization.
The project, valued at approximately 2.1 million PLN, is funded by the state budget reserve. The comprehensive scope of work includes repairing abutments, bridge wings, and span structures, as well as replacing equipment, renewing the surface, and constructing sidewalk curbs. The investment also covers the reconstruction of access roads to improve technical parameters, durability, and user safety. The scheduled completion date for the works is December 10, 2026.