Kruševac implements water supply system for Jastrebac

JKP Vodovod – Kruševac is currently executing works to connect the Jastrebac excursion site to the regional Ćelije water supply system. The project, valued at over 48 million dinars, is funded by the City of Kruševac and the public utility company.

Construction began in July with the completion of rough works on the first 60-cubic-meter reservoir, which includes a hydrofor facility. Final works, such as internal insulation and equipment installation, are currently underway.

The next phase will involve building a second 30-cubic-meter reservoir and a pumping station between the villages of Buci and the existing reservoir. A third phase will focus on establishing remote monitoring and control through integration with the SCADA system to ensure stable water supply to the area.