La Libertad Regional Government risks losing S/ 47.7 million in unrecovered advances

The Comptroller General of the Republic has warned the La Libertad Regional Government (GORE) regarding the potential loss of S/ 47.7 million. These funds consist of advances previously provided to companies for several major projects, including the construction of the new Virú Hospital, the Trujillo-Huanchaco road corridor, and the new GORE institutional headquarters.

Contracts for these projects were terminated due to contractual breaches that hindered physical progress. While a total of S/ 83,262,358 was initially delivered, only S/ 35,578,656 has been amortized, leaving a pending balance of S/ 47,683,701. The Comptroller noted that companies are obligated to return unamortized amounts even after contract termination.

The suspension of these three projects, which were considered emblematic works by former regional governor César Acuña Peralta, has impacted development in the provinces of Trujillo and Virú. Regional authorities stated that actions to recover the funds were initiated prior to the recent alert from the Comptroller.

Entities

Comptroller General of the Republic · César Acuña Peralta · La Libertad Regional Government · Trujillo · Virú Hospital