Low water levels delay Pfaffendorfer Bridge construction in Koblenz
Construction of the new Pfaffendorfer Bridge in Koblenz has faced delays due to low water levels on the Rhine. Two massive steel components, each weighing approximately 475 tons, are currently stuck in the Mannheim Rheinauhafen after completing a six-month pre-assembly process.
Because of their extreme size and weight, the components can only be transported by ship, making road transport unfeasible. The city of Koblenz has indicated that the planned installation at the end of October is no longer possible. Officials are monitoring water levels at Mannheim and Koblenz weekly, hoping for sufficient depth in November to allow for transport.
The bridge project, a vital traffic artery for the city, has been underway since 2023 with an original estimated construction period of five years. The exact completion date for the 311-meter structure remains uncertain.