MBTA to undergo Green Line modernization in November

The Massachusetts Bay Transportation Authority (MBTA) has announced a series of critical infrastructure upgrades for the Green Line scheduled from November 7 through November 15. During this nine-day period, crews will have 24/7 access to portions of the line to expedite modernization efforts.

A primary focus of the work is replacing the legacy signal system in the central tunnel, which dates back to the late 1800s. The project involves installing approximately 16 miles of new signaling cable and 1 mile of fiber optic cable, alongside completing signal system connections and beginning testing at key locations.

These upgrades aim to improve long-term reliability and accessibility. Previous administrations had deferred this work due to its complexity, but the MBTA is now utilizing a phased approach of service diversions to complete the modernization in a cost-efficient manner.