Mexicable Línea 3 construction in Naucalpan reaches 75% completion

The Mexicable Line 3 aerial transport system in Naucalpan has surpassed 75 percent of its construction. The project will link the municipality’s high‑elevation neighborhoods with the Cuatro Caminos Metro station, providing a fast, safe and environmentally friendly alternative for commuters. Municipal President Isaac Montoya highlighted Governor Delfina Gómez Álvarez’s support, noting the line will serve roughly 40,000 passengers each day and cut travel times. Civil works are slated to finish within the current year, with commercial operation expected in the first months of 2027. The line stretches a little over 9.5 km, will include 11 stations after adding Alce Blanco, and will operate 278 cabins that hold ten passengers each, equipped with video surveillance, wireless internet, LED lighting and audio systems. The system is projected to benefit more than 60 communities and about 700,000 residents of the region.

Entities: Cuatro Caminos Metro station · Delfina Gómez Álvarez · Isaac Montoya · Juan Pablo de Botton · Mexicable Line 3 · Mexicable Line 3 · Mexico City Metro Line 3 · Naucalpan

Claims

What the coverage asserts, and how well corroborated each claim is across sources.

  • [● 2 SOURCES] Construction of Mexicable Line 3 in Naucalpan has surpassed 75 % completion. (articles 2e12b2bd-ee9c-40e1-9444-d48b514febdf, d7abbe17-d2ad-4149-991e-1b50afd9d25c)
  • [● 2 SOURCES] Civil works are expected to finish this year with operations starting in early 2027.
  • [● 2 SOURCES] The line’s route is about 9.5 km long and will have eleven stations, including a new Alce Blanco station.
  • [● 2 SOURCES] The project will benefit roughly 60 communities and about 700,000 residents.
  • [○ 1 SOURCE] A public‑private tender to modernise Mexico City Metro Line 3 is valued at over 40 billion pesos.
  • [○ 1 SOURCE] The profit margin for the winning consortium will be set by the competitive bidding committee, with a decision due on 14 September.
  • [● 2 SOURCES] Mexicable Line 3 will serve roughly 40,000 passengers per day.
  • [○ 1 SOURCE] Metro Line 3 transports about 1.1 million users daily and runs from Indios Verdes to Universidad.
  • [● 2 SOURCES] Civil construction will be completed within the current year.
  • [● 2 SOURCES] The line will connect high zones of Naucalpan with Cuatro Caminos Metro station.
  • [● 2 SOURCES] It will benefit over 60 communities and about 700,000 inhabitants.
  • [● 2 SOURCES] The system will serve about 40,000 users daily.